1. Feeding + Crushing system crush rock from 210mm to below 5mm :
Feeding Hopper+Chute Feeder+ Rough Jaw crusher+belt conveyor+Fine jaw crusher+vibration screen+ Roller Crusher
2. Grinding System (grinding material to small powder 200mesh) :
Storage Bin+ Electromagnetic vibration feeder+ belt conveyor+Ball mill+HydroCyclone
3. Leaching Pretreatment :
include Thickener + Agitation tank ( for adjust density of slurry after thickener) +Liner vibrating screen
4. Leaching and Activated Carbon Adsorption processing :
include 2pcs double impeller Leaching agitation tank+ 7pcs double impeller Adsorption agitation tanks+ Roots blower(work for adsorption agitation tank)+ Liner vibrating screen for tailing dewatering+ Liner vibrating screen for screening carbon+ Cabon extractor +Cabon screen
5. Gold-loaded carbon desorption and electrolytic Stage:
Include : normal temperature& normal pressure Elution & Electrolysis system+Drying Oven for gold mud+ Gold smelting furnace
6. Carbon kiln for carbon regeneration
7. Tailing Water recycle system :
High pressure slurry pump+plate filter press+cone slurry tank for making suitable density of slurry before sending to filter
8. FIVE Reagent adding devices system:
each system include reagent agitation tank+reagent slurry pump+ reagent tank.1) Flocculant make-up system for thickener
2) sodium cyanide reagent make-up system for 2pcs leaching agitation tank
3) Lime make-up system for 2pcs leaching agitation tank (for PH control)
4) sodium hydroxide&hydrochloric acid reagent make-up system for cone agitation tank
5) sodium hydroxide&&clean water&sodium cyanide reagent make-up system for Elution & Electrolysis system
9. Water pumps for water supply to complete plant .
1. Slurry Pumps for plant
2. Compelete set electric control pannels
3. Complete set Cables&wires
4. Diesel Generator for plant machines power
5. Complete set Water pipes &slurry pipes